Anman HDL-200C Top-Drive Drill Successfully Completes Complex Foundation Construction Project in Bijie, Guizhou Province
Location: Bijie, Guizhou Province
Drill Model: Anman HDL-200C Top-Drive Drill
Drill Configuration: 180 sets of pipes 89 drill rods
Drilling Method: Anchored drilling
Geological Conditions:
0-2 meters: No layer
2-24 meters: Clay layer
24-27 meters: Medium-fine grained rock layer
27-38 meters: Limestone layer (filled with fillers, prone to collapse)
38-60 meters: Rock layer (medium-fine grained, high-fine grained, and fissured)
Drilling Angle: 30 degrees
Drill Bit Diameter: 200 mm
Drill Depth: 50 meters
Construction Efficiency: 270 minutes
Pure Drilling Time: 180 minutes
Pure Disassembly Time: 56 minutes
![]() | ![]() | ![]() |
1. Assemble the inner and outer pipes in the correct order and according to requirements. Adjust the drill rod position to match the borehole.
2. Start the water pump and slowly advance the drill bit while monitoring pressure changes. The drilling pressure should not exceed the maximum limit, with adjustments made as needed.
3. To clean the pipe, use the downpipe to hold the pipe in place while moving the drill rod up and down to remove any debris. Then, use the uppipe to hold the drill rod and reverse the motor to loosen the drill bit.
4. When installing the drill tool, insert the drill rod into the pipe beforehand and secure it with the downpipe and uppipe. Rotate the interface to connect the drill bit, then open the upper fixture and rotate the pipe to tighten it. Start the water pump and begin drilling. If encountering hard layers, use shock waves as needed.
5. Once reaching the designed depth, clean out the borehole and remove the drill rod (when disassembling the drill rod, slide the outer sleeve up to expose the pipe at the mouth of the borehole, then use the downpipe and uppipe to dismantle). Dismantle the pipe and anchor the anchor rod. If the anchor rod encounters resistance while being lowered into the pipe, use the drill bit to pull out a portion of the anchor rod before lowering it further.
6. Move the drill to the next borehole position, then begin anchoring by pumping cement.