Shandong Jinan MXL-150D2 Rotary Spray Stopping Water
Location: Shandong Province
Location: Jinan City
Drill Model: MXL-150D2
Drilling Configuration: 89 triple screw drill rods
Construction Method: Triple rotary drilling
Geological Conditions: Backfilled soil layer 1-2 meters deep, with soil density of 3-16 g/cm³
Drilling Angle (°): 90
Drill Bit Diameter (mm): 700
Drill Depth (m): 16
Construction Efficiency (min): 120
Pure Drilling Time (min): 10
Pure Disassembly Drill Time (min): 10
Construction Method:
Equipment: MXL-150D2 drill, 89 triple screw drill rods and drill bit head
Backend: 3e120C high-pressure grout pump, ZB2-150 grout pump, spiral air compressor + 0.8 cubic meter storage tank, cement mixing system

Construction Method:
1. Prepare the construction site by leveling and smoothing it.
2. Mark the pile locations according to the design specifications.
3. Position the drill machine to align with the pile location, adjusting its verticality.
4. Prepare the cement grout by filtering it twice and filling the grout pool.
5. Drill the drill rod to the predetermined depth, performing rotary drilling operations: lift speed 12-15 cm/min, rotation speed 12-15 r/min, water pressure 28-30 MPa, grout pressure 1-2 MPa, air pressure 0.7 MPa.
6. Lift the drill bit to the borehole entrance and reduce high-pressure water pump pressure.
7. Remove the drill rod, wash it with clean water, and clean the grout pump, drill rod, and grout pipe, then move the machine to the next pile construction site.