Malaysia SJW-60 Dual Rotary Spray Stopping Water
Location: Malaysia
Drill Model: SJW-60
Drilling Configuration: 89 triple screw drill rods
Geological Conditions: 0-4 meters backfilled (sandstone layer), 4-21 meters mud layer, 21-22 meters gravel layer.
Drilling Angle (°): 90
Drill Bit Diameter (mm): 1000
Drill Depth (m): 22
Construction Efficiency (h): 1.5
Pure Drilling Time (h): 0.08
Pure Disassembly Drill Time (h): 0.08
![]() | ![]() | ![]() |
Construction Method:
1. Adjust the machine to reach the borehole location, ensuring that the bottom of the machine is at the end of the last track (confirming the stability of the machine after completing the borehole).
2. Assemble a 24-meter drill rod and drill to a depth of 22 meters.
3. Use a level to align the drill head's front and back with the left and right sides to 90°.
4. Drill at a speed of 20 r/min, water pressure of 15 MPa, and air pressure of 0.75 MPa for the first 4 meters due to the backfilled soil layer, taking care not to exceed the recommended pressure while elevating the drill rod to ensure verticality at the drill bit's entrance.
5. Continue drilling until the desired depth is reached, paying attention to the borehole's return gas and grout conditions, especially for the first borehole.
6. Elevate the drill rod: grout pressure 25 Pa, air pressure 0.75 MPa (320 kg of cement per meter). Drill speed: 15 r/min. Elevating speed: 13 cm/min.
7. Simultaneously elevate the drill rod and wash the outside of the drill pipe with water to clean it.
8. Finally, lift the borehole an additional 500 mm.
9. Personnel configuration: operator 1, front and back coordination personnel 1, control room staff 1. The backend is fully automated.