Shandong Jinan MXL-150D2 Rotary Spray Stopping Water

2026-04-09 10:40:22 超级管理员 Engineering Case 135 views

Location: Shandong Province

Location: Jinan City

Drill Model: MXL-150D2

Drilling Configuration: 89 triple screw drill rods

Construction Method: Triple rotary drilling

Geological Conditions: Backfilled soil layer 1-2 meters deep, with soil density of 3-16 g/cm³

Drilling Angle (°): 90

Drill Bit Diameter (mm): 700

Drill Depth (m): 16

Construction Efficiency (min): 120

Pure Drilling Time (min): 10

Pure Disassembly Drill Time (min): 10

Construction Method:

Equipment: MXL-150D2 drill, 89 triple screw drill rods and drill bit head

Backend: 3e120C high-pressure grout pump, ZB2-150 grout pump, spiral air compressor + 0.8 cubic meter storage tank, cement mixing system

image.png


Construction Method:

1. Prepare the construction site by leveling and smoothing it.

2. Mark the pile locations according to the design specifications.

3. Position the drill machine to align with the pile location, adjusting its verticality.

4. Prepare the cement grout by filtering it twice and filling the grout pool.

5. Drill the drill rod to the predetermined depth, performing rotary drilling operations: lift speed 12-15 cm/min, rotation speed 12-15 r/min, water pressure 28-30 MPa, grout pressure 1-2 MPa, air pressure 0.7 MPa.

6. Lift the drill bit to the borehole entrance and reduce high-pressure water pump pressure.

7. Remove the drill rod, wash it with clean water, and clean the grout pump, drill rod, and grout pipe, then move the machine to the next pile construction site.